05:58 PM PDT on Monday, June 14, 2004
The city of Riverside Public Utilities is sinking $75 million into a new
power plant that, once constructed, will eliminate the need to purchase
additional power from other companies to meetenergy demand on hot summer
days. The new plant will also help shield the city from electricity
blackouts caused by earthquakes or other natural disasters, or by any
sort of state financial crisis, said Tom Evans, public utilities
director.
For one afternoon in March 2001, the city lost electricity during one of
several rolling blackouts that plagued the state during that year's
energy crisis. Public utility officials asked 20 large electricity users
in the city, including Goodrich, Ralph's markets distribution center in
Sycamore Canyon, Pepsi, Luxfor USA and the University of California,
Riverside, to cut back on their energy consumption in order to continue
distributing power to the rest of the community.
The new power plant, to be called the Riverside Energy Resource Center,
will help eliminate any future need for large businesses to cut back on
electricity consumption during a crisis, Evans said.
The California Energy Commission is holding a second workshop June 17 at
the Riverside Water Quality Control Plant on Acorn Street in Riverside
to hear public comment and Riverside utilities' responses to state
requests for information on land use, traffic, water resources, air
quality and other issues.
The Riverside Energy Resource Center will consist of two 49-megawatt
generators on 12 acres near Van Buren Boulevard and Jurupa Avenue. A
transmission line will be installed about a mile down Jurupa Avenue from
the plant to connect at an electrical substation.
The plant will produce nearly 100 megawatts of electricity, which the
city will use as an additional energy source on scorching days when air
conditioner use jumps.
Generally, one megawatt can provide electricity for 500 to 1,000 homes.
The city requires about 500 megawatts of power on hot summer days, Evans
said.
The resource center's electricity production will eliminate a contract
with the California Department of Water Resources for 50 megawatts of
power, a deal that ends in 2005. The new plant will also eliminate
contracts with the Deseret coal power plant in Utah and with another
company, contracts for a total 50 megawatts which end in 2008-09, Evans
said.
The utilities department will nearly break even on the cost - the
department currently pays 7.5 cents to 8.5 cents per kilowatt hour to
outside firms, and it will cost about 7.5 cents per kilowatt hour to
produce electricity at the new plant.
The benefit is in having the additional electricity source in town, "in
case something goes wrong with the state-wide grid," Evans said.
The utilities department plans to issue bonds to pay for the new plant
and is in negotiations with a company to provide materials procurement
and construction, although Evans declined to identify the firm.
Evans will submit the construction company to the public utilities board
on June 18 with a recommendation for a contract award, he said.
The proposed contract will then be forwarded to Riverside City Council
the first week of July.
Construction on the Riverside Energy Resource Center is expected to
begin in October after state approval and city building permits are
issued.